21-9-26 / Lucinda Brabazon — Building & Construction, Contract
Lucinda Brabazon represented the first defendant, instructed by Preston Law. In 2017, the first defendant entered into a subcontract with the plaintiff to design and construct shoring work for a service station. Shortly after construction, the sheet piling wall collapsed. The plaintiff argued it could set off $151,000, the cost…